Humen Tens Of Billions Of Projects Stop People And Business Accused Of Arrears Of Works

2014/5/24 10:55:00 27

HumenBusinessArrearsWorks

< p > recently, through on-site investigation, and confirmed by many government officials in Dongguan and Humen, Guangdong, a reporter who has invested tens of billions of dollars and has entered Dongguan Humen in a high profile, is now in a state of stagnation due to the lack of funds.

< /p >


< p > as one of the contractors, Hubei South Chu Construction Engineering Co. Ltd. told reporters that people and businesses owed a larger sum of money, but the details were not clear.

< /p >


< p > < strong > scene witnessed: no construction < /strong > /p >


< p > people and business official website information shows that the first phase of the 1st Avenue Project in Humen is located on the ground floor of Binhai Road, with a total area of about 423890 square meters (hereinafter referred to as Binhai Avenue Project). The two phase is located in the city of Dongguan, Bada Avenue, Taiping square, Wen Guang Center and people's Middle Road, with a total construction area of about 228000 square meters.

< /p >


< p > 2012 ~2013, the daily economic news reporter visited the construction site several times and found no signs of construction.

In May last year, the reporter consulted another client. A marketing official told reporters that the Taiping square project will open at the end of 2013 and the Binhai Road project will open in 2014.

< /p >


< p > May 14th this year, the reporter came to Humen again.

Standing in the Humen Park, the land in front is desolate.

Below this piece of land is the starting point of human and commercial Binhai Road project.

Because of the long exposure to sunlight and rain, the billboards used to block underground outlets have been damaged.

< /p >


< p > looking down through the cracks in billboards, there is a pool of water in the low-lying areas connected with underground shopping malls, and some rusty iron nets are stacked next to them.

The temporary construction of the building near the Humen park is surrounded by weeds, and the room is empty.

< /p >


< p > a two story orange building is one of the few ground matching projects.

There are many holes in the glass curtain walls and windows of the "small building". The entrance to the road only has a doorframe, and the stairs leading to the two floor have not been repaired. The billboards originally used for blocking are scattered outside the door.

It is understood that this building may later serve as the office building of the 1st Avenue.

< /p >


< p > in the impression of many residents near Humen Park, Di Yi Avenue is a project that has existed for a long time and has been closed down.

< /p >


< p > "the project hasn't been finished yet. It's been a long time."

A security guard told reporters at Humen park.

< /p >


< p > then, the reporter came to the Taiping square project which was separated from the Humen town government.

It was difficult to find traces of construction due to the fact that the pit was excavated.

< /p >


< p > the door of the investment center on the side of the square is empty. The reporter walked in. There were no salesmen in it. Several security guards and water electricians were chatting. The sand table in the middle of the room was covered with a layer of plastic cloth.

A northern accent guard told reporters, "it rained a few days ago. The construction seems to have stopped. It used to be dug down every day."

He refused to go underground to see the progress of the project.

< /p >


< p > < strong > Sales Manager: the progress of Humen project is slow. < /strong > < /p >


< p > in fact, the human and commercial Humen project is one of the commercial projects built in the name of civil air defense project. It was launched in March 2011.

< /p >


< p > Dongguan people's Air Defense Office personage to the "daily economic news" reporter, by the national family Defense Office, the provincial people's Defense Office and the municipal government agreed to build Binhai Avenue and Humen Avenue below the underground public air defense works of Humen Binhai Road, the total construction area of about 710 thousand square meters, divided into two phases of construction, Binhai Road project is phase I, Taiping square project is the two phase.

< /p >


Under the guidance of the locals, reporters found the investment center of the one Avenue business. The reporter expressed his investment intention to a sales manager as a client. The customer manager recommended that P reporters go to other projects.

"The progress of Humen project is relatively slow. If it is urgent, we can see the rich people across the river, or look at the two phase of our Guangzhou project."

< /p >


< p > the customer manager said, "we are responsible for investment promotion. The opening time depends on the progress of the project.

Now the main works have been completed and the interior decoration is being carried out.

< /p >


"P," another sales manager said, "because last year we started the expansion of the two phase of Guangzhou project. The company should do that (Guangzhou) well and come back to do this (Humen).

Therefore, the Humen project will be postponed this year, and it may come to the Ming and the following year.

Another reason is that the subway near Binhai Road is still being repaired, and the progress of people and projects follows the subway.

However, the progress of Taiping square project is faster, and it will strive for opening in September 1st.

< /p >


< p > reporter repeatedly tried to contact the former Humen project marketing director, the phone has been shut down.

The 400 investment hotline provided by people and commercial official website can not be connected.

People and commercial Harbin headquarters and Beijing companies are reluctant to be interviewed by reporters.

< /p >


< p > May 19th, the reporter once again called the Guangzhou road one avenue investment center telephone as a client.

A sales manager said, "the Humen project involves cooperation with the government. The situation is complicated and there is no more details."

< /p >


< p > < strong > Civil Air Defense Office: initial plan duration is only half a year < /strong > /p >


< p > now, the Humen project has been postponed again and again because of human and business < a href= "//www.sjfzxm.com/news/index_c.asp" > capital < /a > tension? < /p >


< p > Hubei South Chu Construction Engineering Co. Ltd. told reporters that people and Commerce have not yet settled most of the projects.

< /p >


< p > reporter found and found the Dongguan civil air defense office. A staff member of the engineering department who participated in the project supervision told reporters that the underground public air defense works of Humen pformed by man and commerce were divided into ten tenders. Only one section of the civil air defense works was normally constructed. The main project of Hama Mio road completed 90%, which has been used as a pedestrian crossing and parking lot.

However, he stressed, "we say the main project is based on the standards of civil air defense engineering, and now it is a reinforced concrete platform. Later, the commercial area needs to be divided into walls and decoration."

< /p >


"P," he further said, "every project is rich and smooth.

We are unable to manage people and businesses economically, and have not signed any contracts with them. We can never give money to them to start work, but to supervise them in accordance with the norms of civil air defense.

< /p >


< p > another human defense office staff said that the initial plan for human and business was only half a year, but < a href= "//www.sjfzxm.com/news/index_c.asp" > Humen < /a > underground structure and geological conditions were relatively poor.

Over the past few years, the stock of the company has fallen sharply, and it has not been able to borrow money from the bank.

< /p >


Wang Ming, a government official of Humen town who was contacted with < a href= "//www.sjfzxm.com/news/index_c.asp" > man and business < /a >, recalled to reporters that "in 2010, the Humen government confirmed the winning bid of people and business as a civil air defense project through tender, and soon began large-scale construction."

However, it was unexpected that the massive project failed to complete because of the pressure of funds.

Wang Ming frankly said that in the second half of 2012, the Humen government found that the progress of Humen's underground works was slow. It was only necessary for people and businesses to resume surface works, without affecting the normal travel of the citizens.

< /p >


< p > "there is no way for them to stop working.

At the beginning, the leaders thought that such a big investment could drive the economy of Humen. Now, Lao Wu (former Secretary of the Humen Town Committee of Dongguan, Wu Zhi Hui, has now fallen off) has had an accident.

Wang Ming said.

< /p >


< p > reporter tried to contact the Propaganda Department of Humen Town, key project construction office, construction safety supervision station and other relevant departments to track the cause of the Humen project shutdown, and the results were all "unclear".

< /p >


< p > although people have questioned the company's capital and business models, people and businesses still do not accept any media coverage.

< /p >

  • Related reading

Cross Border Expansion Of Guangzhou Department Stores Meets "Curse" Again

Project Finding Funds
|
2014/5/23 18:46:00
36

新光百货南海店撤离佛山

Project Finding Funds
|
2014/5/21 14:05:00
35

福州地下商场不景气 万宝商圈地下综合体能否“破冰”

Project Finding Funds
|
2014/5/14 9:11:00
53

Construction Of New Textile And Garment Industry In Southeast Henan

Project Finding Funds
|
2014/5/3 16:17:00
66

Nantong Textile Academy Approved Jiangsu University Collaborative Innovation Center

Project Finding Funds
|
2014/4/24 16:21:00
397
Read the next article

Shops Return To Tradition To Avoid Competition In Department Stores

The commercial complex is actually an extension of the bottom floor. But blindly pursuing tall buildings is actually making the space smaller and smaller. It is better to be the neighborhood center of the community and provide more complete facilities to the owners. Then, in the next time, everyone will follow the world's clothing and shoe net to see the detailed information.